Check the Available AACE-PSP Exam Dumps with 120 QA’s UPDATED 2024 [Q49-Q65]

5/5 - (1 vote)

Check the Available AACE-PSP Exam Dumps with 120 QA’s UPDATED 2024

Download AACE-PSP Exam Dumps Questions to get 100% Success in AACE International 

NEW QUESTION 49
Resource planning must take all of the following into account except for

 
 
 
 

NEW QUESTION 50
Identify the minimum project duration.

 
 
 
 

NEW QUESTION 51
Scenario:
The entire network consists of the following activities and relationships. Activity A is twenty days long and is tied to Activity B, a ten-day activity, with a finish-to-finish tie with a lag value of five Activity B is tied to Activity C, a twenty-day activity, with a start-to-start relationship with a lag value of five.

PSP Activities Table
Scope Known about Rock-Filled Dam Project:
The dam requires river diversion and work over two or more rainy seasons. The contract is lump sum, competitively bid, and will be self-performed. The owner has attempted to shift all risk to the contractor by employing “no differing sit conditions” and “no damage for delay” clauses. There is a bonus/penalty provision of $2,500 per calendar day for early or late delivery. The early completion bonus is capped at $500,000, with no cap for late delivery penalty.
Liquidated damages end at the finish of demobilization. Indirect costs per calendar day are $2,800 for the
“normal” schedule and $3,200 for the “crashed” schedule. The winter/wet weather season is 151 days between October 15 and March 25 of each year, reduces the efficiency of the contractor’s operations by 20% and costs the contractor $10,000 per day. Assume a start date of March 5, 2001 and use a 7-day work week.
The following table lists work activities as planned by the contractor.

Theoretically construct a summary activity for only those activities with a finish-to-start relationship for Activities 8001 through 10001. Using the “normal” schedule, what is the cost of this hammock?

 
 
 
 

NEW QUESTION 52
Theoretically construct a summary activity for activities 2001 through 2004. Using the “normal” schedule, what is the cost of the hammock?

 
 
 
 

NEW QUESTION 53
The expected remaining cost needed to complete an activity, group of activities or the project is the____________.

 
 
 
 

NEW QUESTION 54
If drafting of the product manual overruns its planned duration by 5 days, how many days may the manufacturing be delayed without affecting release of the product?

 
 
 
 

NEW QUESTION 55
If Activity E’s duration changes to 4 months, what is the overall duration of the project.

 
 
 
 

NEW QUESTION 56
Determine the correct formula and date for the late finish for Activity 9004.

 
 
 
 

NEW QUESTION 57
Which of the following phases does NOT describe the commonly accepted construction life cycle?

 
 
 
 

NEW QUESTION 58
Which of the following will always describe the critical path? The path with

 
 
 
 

NEW QUESTION 59
Free float is the

 
 
 
 

NEW QUESTION 60
Which of the following is NOT input data to the construction planning process?

 
 
 
 

NEW QUESTION 61
What was the original planned duration for Activity A through Activity G?

 
 
 
 

NEW QUESTION 62
Determine the correct formula and date for the late start for Activity 9001.

 
 
 
 

NEW QUESTION 63
Which of the following project planning situations is the most frequent contributor to cost overruns?

 
 
 
 

NEW QUESTION 64
If no time extensions are granted and all actual delays are as described above, what will the total float calculation be at the end of the project?

 
 
 
 

NEW QUESTION 65
Using the “normal” schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

 
 
 
 

Best Value Available! 2024 Realistic Verified Free AACE-PSP Exam Questions: https://www.real4prep.com/AACE-PSP-exam.html

         

Related Links: www.stes.tyc.edu.tw www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt www.stes.tyc.edu.tw myportal.utt.edu.tt

답글 남기기

이메일 주소는 공개되지 않습니다. 필수 필드는 *로 표시됩니다

아래 이미지에서 텍스트를 입력합니다.